New solar farm in Edison comes online in December

03 Jan 2017 10:03 AM | Anonymous member (Administrator)
by Pamela MacKenzie, My Central Jersey


Public Service Electric & Gas, New Jersey's oldest and largest publicly owned utility, is about to bring a new solar farm online in Edison.

This solar array, which will produce 7.75 megawatts of power — enough to power 1,300 homes — is one of the last sites to come online in the current phase of the utility's Solar 4 All program. When completed, PSE&G will be generating nearly 125 megawatts of power through the Solar 4 All program, which includes arrays on utility poles in North, Central and South Jersey (40 megawatts) and other solar facilities on buildings, brownfields and other sites.

The new solar array, which has been under construction since June of 2016, is built on the old ILR landfill. It is PSE&G's second solar farm on a landfield or brownfield in Edison. The first was at the PSE&G-owned Silver Lake site at the foot of Silver Lake Avenue, which was polluted around the time of the Civil War.

...

For the entire article, see http://www.mycentraljersey.com/story/news/local/how-we-live/2016/12/17/new-solar-farm-edison-comes-online-month/95331544/


Upcoming Events

Search Our Website


Address:
c/o Cherrytree Group
287 Auburn Street
Newton, MA 02466

Phone: 833-240-0208

Click to Send Us an Email

Connect With Us


Brownfield Coalition of the Northeast is a nonprofit organization 501(C)(3) and all gifts are tax deductible to the extent allowed by law.
Every contributor to our Organization is recommended to consult their tax advisor for further information.

Powered by Wild Apricot Membership Software