By Daviid M. Zimmer, NorthJersey.com
Nearly two years since the delayed $18 million surface contamination cleanup started at the Ringwood Mines Superfund site, a finish line remains months away.
The project, which started in November 2021 and was expected to take one year to complete, has been mired in delays stemming from faulty survey data. Officials at de maximis inc., the firm hired by Ford Motor Co. to coordinate the cleanup, said work could nonetheless resume on the soil cap for the borough-owned O?Connor Disposal Area landfill later in October or November, records show.
Geotextile caps have already been installed at the site's two other areas of concern, the Cannon Mine and Peter's Mine pits. Used along with the disposal area to dump paint sludge, chemical solvents and other toxic waste from Ford?s former Mahwah factory, the pits were initially part of a working network of iron mines.
For the entire article, see
https://www.northjersey.com/story/news/passaic/ringwood/2023/10/16/ringwood-mines-superfund-site-delays-surface-cleanup/71147910007/